• Acronym:
    HYDROGIN
  • Coordinator:
    dr inż. Marek Skrzypkiewicz
  • Duration:
    28.06.2019 - 20.06.2023

Description

Goal: Development, construction, and testing of a containerized installation with rSOC cells with a capacity of 10kWe based on a stack of solid oxide electrochemical cells (SOC) operating in electrolyzer mode. The system is also designed to operate in reversible mode with a hydrogen generation efficiency of at least 70% in SOE mode, electricity generation efficiency of at least 60%, and a possible overall energy storage efficiency in the electricity-hydrogen-electricity cycle of 42% (round-trip efficiency). The unit, integrated with a combined heat and power plant, is in the form of a 20-foot container.

Budget: 2 250 000 PLN

We use cookies

We use cookies on our website. Some of them are essential for the operation of the site, while others help us to improve this site and the user experience (tracking cookies). You can decide for yourself whether you want to allow cookies or not. Please note that if you reject them, you may not be able to use all the functionalities of the site.